News On Japan

Hokkaido Shinkansen Sapporo Extension Delayed by 12 Years

SAPPORO - The long-delayed extension of the Hokkaido Shinkansen to Sapporo is facing further setbacks, with the opening now pushed back by more than a decade and total project costs projected to more than double, even as construction steadily advances on the ground.

Nearly 10 years have passed since the Hokkaido Shinkansen made its high-profile debut, linking Honshu and Hokkaido through the Seikan Tunnel in March 2016, when a special service emerged from the tunnel to mark the arrival of bullet trains on the island.

At the time, the plan envisioned trains running between Sapporo and Tokyo in 4 hours and 49 minutes within five years, but the Sapporo extension has since been delayed repeatedly and is now expected to open no earlier than fiscal 2038.

At the same time, total project costs are forecast to exceed twice the original estimate, prompting questions about why expenses have ballooned and how the massive undertaking is progressing.

East of Sapporo Station, stretching toward Naebo Station, a massive structure is under construction that will serve as a dedicated Shinkansen rolling stock depot for Sapporo, a site that a year ago held little more than rows of construction vehicles.

For the first time, television cameras were allowed inside the depot construction site, where the facility is being built on elevated structures, an arrangement with few precedents nationwide for Shinkansen depots.

Inside a vast sheltered space, Shinkansen trains will eventually be parked, with the area beyond set to become JR’s Sapporo Shinkansen Station, while a 1,344-meter-long depot will be located on the eastern side of the station, spanning National Route 5 and Soseigawa-dori.

The depot is designed to accommodate three full train sets side by side, with elevated structures around 60 percent complete as of January 1st, and work now progressing on the slabs that will form the track bed for Shinkansen operations, according to officials from the Japan Railway Construction, Transport and Technology Agency.

Once completed in about two years, the depot will be covered by a protective shelter to guard against snow and harsh weather, a shape that has already earned it the nickname “an eel’s sleeping quarters” among rail enthusiasts.

The route between Shin-Hakodate-Hokuto and Sapporo spans roughly 212 kilometers, with about 80 percent running through tunnels, leading some to dub it the “mole Shinkansen.”

One of the largest challenges is the Satsutari Tunnel, which cuts beneath Otaru and Sapporo and stretches more than 26 kilometers, where excavation continues around the clock, with rock blasted twice a day and carried out by conveyor belts.

From the tunnel entrance in Teine Ward’s Kanayama district, work has advanced about 1.2 kilometers toward Otaru, with the tunnel’s basic shape largely complete despite the absence of tracks or rivers at this stage.

Overall progress on the Satsutari Tunnel stands at just under 60 percent, with construction now running about three years behind the original schedule, as crews reinforce tunnel walls by inserting bolts at regular intervals, allowing excavation to advance by up to six meters per day.

According to the railway agency, excavation has been completed in 10 of the 17 tunnels along the route, but progress has not been uniform, with major rock formations discovered in tunnels such as the Yotei Tunnel in the Shiribeshi region, significantly complicating construction.

Rising material prices, higher labor costs, and tighter regulations on workers’ hours have further prolonged the project, pushing the estimated total cost from an initial 1.67 trillion yen to more than 3.5 trillion yen in the latest projections.

For local governments, the cost increase has brought fresh concerns, particularly in towns like Yakumo, where a planned station tentatively named “Shin-Yakumo Station” will be located about three kilometers from the town center.

Under the current framework, two-thirds of the construction costs excluding JR’s loan payments are covered by the national government, with the remaining third borne by Hokkaido and municipalities along the route.

Yakumo Mayor Toshimi Mantani said the town had initially expected to shoulder around 800 million yen, but that figure is now projected to rise by roughly 400 million yen to about 1.2 billion yen.

While the station is expected to place Yakumo within about 50 minutes of Sapporo and directly connect the town to Tokyo, with officials envisioning Japan’s first Shinkansen station “in the middle of a ranch,” the burden of local infrastructure development, including water and sewer systems around the station, is weighing heavily on the municipality.

Mantani said Yakumo and other communities along the line plan to urge the national government to accelerate the project and reduce local financial burdens as much as possible.

Among local residents, anticipation and unease coexist, with longtime restaurateur Naoki Shinohara recalling how he created an original curry inspired by Yakumo a decade ago, eager for the day the Shinkansen would arrive, only to see the timeline pushed back again.

Shinohara said he still struggles to reconcile the idea of delays driving money out of the town, but hopes increased tourism will eventually materialize, adding that he wants to stay optimistic despite the uncertainty.

As questions persist over whether costs will rise further and whether Sapporo can indeed be linked to Tokyo within the next 12 years, construction on the Hokkaido Shinkansen continues amid mounting challenges.

According to broadcasters, the 212-kilometer route between Shin-Hakodate-Hokuto and Sapporo includes 17 tunnels, with estimated travel times of about 25 minutes to Kutchan, 50 minutes to Yakumo, and around 1 hour and 5 minutes to Shin-Hakodate-Hokuto.

Yakumo, which faces a severe shortage of doctors, is also hoping that becoming a day-trip distance from Sapporo will make it possible for physicians to commute, potentially easing local healthcare shortages.

Commentators noted that while dramatically shorter travel times could boost exchanges between regions, the project’s swelling costs, now exceeding Hokkaido’s annual budget of roughly 3 trillion yen, have elevated the Shinkansen extension into a major political issue for the region, underscoring the need to balance convenience, safety, and fiscal responsibility as the project moves forward.

Source: HBCニュース 北海道放送

News On Japan
POPULAR NEWS

Large Typhoon No. 25 was moving northwest over waters south of Japan at 3 p.m. on September 19 and is forecast to strengthen as it approaches Kanto and the Izu Islands from September 20 through September 21, bringing the risk of torrential rain, violent winds and further damage in areas still recovering from last year's typhoon.

A black bear has been spotted near one of the most popular hiking trails on Mount Takao in western Tokyo, prompting authorities to urge visitors to take precautions ahead of the five-day Silver Week holiday and the approaching autumn foliage season.

Starbucks is considering selling a majority stake in its Japanese business, potentially valued at as much as $3 billion, or about 470 billion yen, as the U.S. coffee chain seeks to concentrate management resources on its struggling North American operations.

Japan's Halloween Jumbo Lottery went on sale nationwide on September 16, offering a combined top payout of 400 million yen for the first prize and its adjacent-number prizes.

A new top-tier "Supreme Class" offering fully private compartments above the level of Green Car service will debut on the Tokaido and Sanyo Shinkansen on October 1, with passengers able to experience the new seating at a demonstration booth at Shin-Osaka Station.

MEDIA CHANNELS
         

MORE Travel NEWS

The Kyushu Shinkansen will resume operations along its entire route on September 18 after suffering extensive track and other damage in the Kumamoto earthquake, raising hopes that the long-awaited restoration will help revive tourism in disaster-hit areas ahead of the Silver Week holiday period.

Prolonged rain is disrupting tourism ahead of Japan's Silver Week holidays, forcing Nagatoro's popular river cruises to remain suspended for an 11th consecutive day while increased water flow at Fukuroda Falls in Ibaraki Prefecture is drawing more visitors.

A new top-tier "Supreme Class" offering fully private compartments above the level of Green Car service will debut on the Tokaido and Sanyo Shinkansen on October 1, with passengers able to experience the new seating at a demonstration booth at Shin-Osaka Station.

Tokyo Disney Resort will launch its annual Disney Halloween event on September 16, with a special parade previewed ahead of the opening and visitors allowed to enjoy the parks in costume during the event period.

Visitors can climb to the top of the Akashi Kaikyo Bridge, about 300 meters above the sea, for sweeping 360-degree views of the Akashi Strait, Kobe, Awaji Island and, in clear weather, as far as Osaka.

A mobile battery caught fire inside a Tobu Isesaki Line train in Saitama Prefecture on September 14, leaving a high school student with minor burns before another passenger extinguished the flames.

GO, Waymo and Nihon Kotsu said they aim to launch Japan's first commercial fully driverless taxi service in Tokyo during 2027, using Level 4 autonomous vehicles that can operate without a driver on board under specified conditions.

Kajima Corp. has unveiled the construction site of KAJIMA TREE, a roughly 60-meter wooden tower being built for the International Horticultural Expo that will open in March 2027.